Case study 01 · Production

Simplifying standards and standardising allocation

A European manufacturer with highly complex and frequently updated production plans approached PeoplePlan to translate those plans into manning, and assist with more efficient allocation of employees to approximately 1,000 roles per week. The results were tighter controls on manning, streamlined processes and a shift plan easily shared with the team on the factory floor.

Roles per week
Approx. 1,000
Plan updates
Multiple daily
Planning
Automated
A production line at a manufacturing site
A shift plan that can be shared with the team on the factory floor.

The full story

From complex production plans to dynamic manning

01

Background

The site production plan, whilst detailed and complex, only gave visibility of production. In addition to the product manning, there was a need to identify and generate manning for preparation roles, changeovers, cleans and shutdowns.

Employee availability was being manually checked, the allocations done by hand, then work schedules had to be entered back into the workforce HR and payroll system.

The site team had been unable to implement their required solution in legacy workforce management systems.

02

The challenge

The site’s existing planning processes involved complex manual processes and duplicated effort:

  • Converting production plans to manning standards was complicated and open to error.
  • Allocation to jobs was done manually, with added duplication of effort entering schedules back into payroll systems.
  • Communication of plans was inefficient.

The new solution needed to automate the creation of manning standards, streamline the processes through integration with other business-critical systems and share the production plan in a format familiar to the team on the factory floor.

03

Our approach

PeoplePlan worked with the labour planners and stakeholders to translate the manning standards into system rules and reporting.

The new solution uses the bespoke manning rules to automatically translate production plans into the labour requirements for each shift, handling multiple production plan updates per day to keep requirements in line with production changes.

Custom allocation rules based on availability, skills and working time regulations are used to assign employees to the jobs. Allocation takes into account local prioritisation and fairness rules. Factors considered include job priority by work area grouping in explicitly specified orders, employee work patterns and training levels. Consideration is even given to the jobs least recently worked per individual, to ensure freshness of skills and experience.

PeoplePlan facilitates flexibility of the actual times the jobs run, allowing for separate job times for individual work areas and individual roles to spread resource along the workflow as and when production reaches each stage of the process; for example, during a morning start-up after a weekend of stand down.

Finally, PeoplePlan provides data to the existing workforce and HR systems to ensure data accuracy and consistency throughout the business, eliminating entry duplication.

Bespoke rules, applied automatically

Manning standards become system rules, so every plan update produces labour requirements for each shift without rebuilding the plan by hand.

04

The outcome

More reactive planning

Vastly reduced planning time and the ability to more easily handle frequent plan changes.

Improved accuracy

Detailed, granular manning rules cover a wide variety of scenarios, and variations to standards are auditable.

Elimination of duplication

Labour planners no longer need to spend time entering schedules back into HR and payroll systems.

Shared visibility

Plans are quickly and easily shared with the workforce.

What happened next

The manning rules extended to time-specific job requirements, and the site team continue to work in partnership with PeoplePlan to refine and update manning rules as business needs evolve.

A similar brief?

Tell us what your operation needs to plan better

We will talk through your current process, the gaps you can see and what a realistic delivery would look like for your sites.